Dallas City Council approved, as amended, up to $3 million in ARPA funds to study up to four possible sites for relocating city hall staff, 911, and emergency operations from 1500 Marilla Street.
Committees mentioned
Open the committee coverage hubs tied to this summary.
Topics discussed
Was this summary helpful?
Your feedback helps us prioritize what to improve next.
What this means
The council authorized the city manager to negotiate pre-acquisition agreements for due diligence on up to four sites. The work is meant to assess whether city hall staff, 911, and emergency operations could move from 1500 Marilla Street. The council also shifted up to $3 million total from an existing ARPA repair line item to pay for this review. The city manager must bring the findings back to council for review.
Key decisions
Follow the major takeaways from this briefing.
- Approved as amended a resolution to study relocation options for city hall staff and functions from 1500 Marilla Street.
- Approved as amended a resolution to study relocation options for 911 and emergency operations staff and functions from 1500 Marilla Street.
- Transferred up to $2,000,000 for city hall site due diligence from the ARPA City Hall Generation and Electrical Repair line-item to a new ARPA City Hall Pre-Acquisition line-item.
- Transferred up to $1,000,000 for 911 and emergency operations site due diligence from the ARPA City Hall Generation and Electrical Repair line-item to a new ARPA City Hall Pre-Acquisition line-item.
- Directed the City Manager to return the due diligence results to City Council for consideration.
Timeline & follow-ups
Action items flagged by the community.
No follow-ups have been shared yet. Add one in the community board below.
Meeting information
Details and records from this meeting.
Recent documents
Fresh records from this municipality.
Civic leadership
Know who to contact about the decisions that matter.